National Accounts

Canopies Delivered Straight to Every Job Site

SKYSCAPE® canopies travel by dedicated truck through our freight partners and are delivered directly to you. Fabrication takes 4 to 5 weeks, and delivery typically takes 1 to 4 days depending on location.

Starbucks building under construction in Liberty, Missouri, with SKYSCAPE canopies over the storefront

Shipping at a Glance

4 to 5 weeks Fabrication
1 to 4 days Delivery, depending on location
U.S. and Canada Nearly all of the 48 contiguous states, plus Canada
About 90% Ready to install when it arrives
Freight

How Your Canopies Ship

Every SKYSCAPE® order ships on a dedicated truck through our freight partners and is delivered directly to you at each job site.

Dedicated trucks

Shipped on its own truck

Your order travels as a dedicated truck shipment through our freight partners, then goes straight to your site.

Protection

Wrapped, boxed and palletized

Large products are wrapped and protected for the trip. Smaller items are boxed and palletized.

On arrival

About 90% ready to install

Each canopy is pre-welded, factory-assembled and finished in house. Only a few accessory items, such as hanger rods and wall plates, are attached in the field.

Shop drawings come with every order, so the crew on site can confirm the right canopy goes in the right location. Most canopies can be unloaded by 2 to 4 people, depending on size, without special equipment or a forklift in most cases. See the canopy FAQ.

Lead Time

From Release to Delivery

The clock starts when fabrication is released. Shipment schedules depend on approved shop drawings, all necessary field dimensions and a written release for fabrication, and the lead time for your project is confirmed on your official quote.

Step One

Approval and release

Shop drawings are approved, field dimensions are in, and fabrication is released in writing. See the submittal and shop drawing process.

Step Two

Fabrication, 4 to 5 weeks

The canopy is extruded, welded and finished in our own facility, with a powder coat meeting AAMA 2604.

Step Three

Delivery, 1 to 4 days

A dedicated truck carries the order to your site. Transit typically takes 1 to 4 days, depending on location.

Step Four

Unload and install

A small crew unloads it on site, and installation follows a few simple steps.

Multi-Site Projects

Phased Deliveries for Rollouts

On a multi-location rollout, deliveries are phased and timed to each site's readiness. Each location receives its canopies when it is ready for them, instead of every order arriving at once.

The canopy standard stays the same from site to site, while the engineering is done for each location's own wind and snow loads. For how a multi-location rollout runs from prototype to delivery, see national account canopy programs.

Red SKYSCAPE canopy over the entrance of a CubeSmart self-storage building in Lenox, Pennsylvania, under construction
CubeSmart, Lenox, Pennsylvania, in progress.
Coverage

Where We Ship

We ship to nearly all of the 48 contiguous states, and to Canada. Orders for Hawaii and Alaska ship by dedicated truck to a West Coast port, then continue by container.

A few of the projects in progress from our in-progress gallery:

Dark aluminum canopy over the storefront of Birches Self Storage in Ogden, Utah
Birches Self Storage, Ogden, Utah
Aluminum canopy over the ground floor glazing of the Exchange II multi-family building in Buffalo, New York
Exchange II, Buffalo, New York
Post-supported aluminum canopy along the storefronts of Boardman Plaza in Cleveland, Ohio
Boardman Plaza, Cleveland, Ohio
Aluminum canopy wrapping the storefront of a Starbucks under construction in Liberty, Missouri
Starbucks, Liberty, Missouri
After Delivery

Installation, Wherever the Site Is

  • Within a 300-mile radius of Atlanta, SkyScape's own crews install the canopies.
  • Beyond that radius, we work with a nationwide network of installers.
  • Many general contractors choose to use their own labor or local subcontractors.

Because each canopy is welded, not thru-fastened, the installation instructions run to a few simple steps. See what contractors and installers receive, including a 90-second installation video.

Installers on ladders fitting a post-supported aluminum canopy at the T-Mobile call center in Augusta, Georgia
T-Mobile Call Center, Augusta, Georgia, during installation.
Common Questions

Shipping and Delivery Questions

Fabrication takes 4 to 5 weeks. Delivery then typically takes 1 to 4 days, depending on location. The lead time for your project is confirmed on your official quote.

Through our freight partners, as dedicated truck shipments delivered directly to you.

Large products are wrapped and protected. Smaller items are boxed and palletized.

Yes. On a rollout, deliveries are phased and timed to each site's readiness.

To nearly all of the 48 contiguous states, and to Canada. Orders for Hawaii and Alaska ship by dedicated truck to a West Coast port, then continue by container.

SkyScape's own crews install within a 300-mile radius of Atlanta. Beyond that, we work with a nationwide network of installers, and many general contractors choose to use their own labor or local subcontractors.

Plan Deliveries for Every Job Site

Send your project details or your site list to start a quote. Lead times for your project are confirmed on the official quote.